Bridgend Ford Wind Turbine

Bridgend Ford Wind Turbine

Awarded to iFix Reinforcements Ltd by AE Yates Group in 2014.

The project awarded consisted of a turbine base, stairway and kiosk. The total tonnage of the base was 18 tonne with 320 m3 of concrete. With the expertise of the iFix workforce this project took no time to finish. With just 2.5 days for the steel fixing and pekafil alone, and half a day for the shuttering around the can, and day for the concrete pour. The concrete finish was of a high spec which was highly respected by AE Yates Group. Although this project was small, iFix put in 100% effort, safety and clients satisfaction into this project as we do on any project rewarded.

 



AE Yates

Bridgend Ford wind turbine


Bridgend, South Wales